Engineering·November 23, 2026·10 min read

Apple rejected 23% of app submissions in 2025. How a non-technical founder plans a launch date around App Review

Apple rejected 2.09M of 9.1M app submissions in 2025, and Google makes new personal accounts test for 14 days. Plan launch around both.

Apple's App Review rejected 2,093,244 of the 9,100,620 app submissions it reviewed in 2025, about 23%, according to Apple's own 2025 App Store Transparency Report. Google Play adds a different gate: a new personal developer account cannot publish to production until 12 testers have been in a closed test for 14 days straight. If you are a non-technical founder paying for a mobile build, those two facts belong in your launch plan before anyone books the launch party.

Most founders set the launch date from the day the build is "done." The date that matters is the day both stores say yes, and the work that decides it (who owns the developer accounts, whether a reviewer can log in, whether your testers are lined up) is mostly paperwork your developer may not raise unless you ask.

What Apple's 2025 numbers say about rejection

Apple publishes an App Store Transparency Report every year. The 2025 edition counts:

Measure (calendar 2025)Count
App submissions reviewed9,100,620
App submissions rejected2,093,244
Rejections citing the Performance section1,354,418
Rejections citing the Legal section495,673
Rejections citing the Design section415,532
Rejections citing the Business section283,820
Rejections citing the Safety section151,159
Submissions approved after rejection387,087

Two caveats Apple states in its own footnotes. A submission is not an app: one app can be submitted many times, and every update is a new submission. And a rejection can cite more than one guideline section, which is why the section counts add up to about 2.7 million against 2.09 million rejections.

Even with that overlap, one section dominates. Performance was cited in rejections equal to about 65% of the 2025 total, and the 2024 report shows the same shape: 1,235,471 Performance citations against 1,931,400 rejections out of 7,771,599 submissions. The overall rejection rate barely moved, from about 24.9% in 2024 to 23.0% in 2025.

So the honest planning assumption is not "we'll probably sail through." Roughly one submission in four or five comes back, and the most common reason is in the section you can control.

Why "Performance" rejections are the founder's problem, not the developer's

"Performance" sounds like slow code. In Apple's App Review Guidelines it is section 2, and it opens with guideline 2.1, App Completeness. That guideline asks for things that sit with the business as much as with the engineers:

  • A working demo account. Apple asks you to "include demo account info (and turn on your back-end service!) if your app includes a login." If the reviewer can't get past your sign-in screen, they can't review the app.
  • No placeholder content. Placeholder text, empty websites and "other temporary content should be scrubbed before submission." The privacy policy link that points to a half-built marketing site counts.
  • Accurate metadata. Guideline 2.3 asks that your description, screenshots and privacy information "accurately reflect the app's core experience."

Two more rules catch first apps often enough to check by name. Guideline 5.1.1(v) says that if your app supports account creation, "you must also offer account deletion within the app." And guideline 4.2, Minimum Functionality, says an app should "elevate it beyond a repackaged website." A login screen wrapped around your existing web dashboard is the classic case.

None of these is an engineering judgment call. A founder can own every one of them on a checklist.

How long Apple and Google take to approve a first app

Apple: usually days, plus a resubmit

Apple's App Review page says it "typically" reviews at least 50% of submissions in under 24 hours and 90% in under 48 hours, and warns that incomplete submissions may take longer. That is a typical figure across all submissions, mostly updates from established developers. Apple does not publish a separate figure for a company's first app, so don't plan as if you will be in the fast half.

A rejection costs more than the review time. Someone has to read the reviewer's note, fix the build or the metadata, and submit again, which puts you back in the queue. Apple's report counted 387,087 submissions approved after rejection in 2025, about 18.5% of the rejections. Read that as the good news: a rejection is usually a list of fixes, not a verdict on the business.

Google Play: a fixed 14-day test for new personal accounts

Google's rule is easier to plan for, because it is a fixed clock. Its Play Console Help page says developers "with personal accounts created after November 13, 2023, must run a closed test for their app with a minimum of 12 testers who have been opted in continuously for at least 14 days." Only then can you apply for production access, and Google says that review "usually takes seven days or less, but can occasionally take longer."

That is three weeks of calendar time you cannot compress with more engineers. Twelve real people, opted in for 14 continuous days, then up to a week of review.

The rule names personal accounts. An organization account is a different enrollment, and it asks for a D-U-N-S number from Dun & Bradstreet, which Google notes is free to obtain. Check Google's current requirements for your account type before you assume either path, because the testing rule is the part founders discover too late.

Who should own the developer accounts

Our opinion, and one we would defend on any first call: the Apple and Google developer accounts should be enrolled in your company's name, not your developer's. Apple's enrollment page for organizations says the organization's name "will be displayed as the seller name of your apps on the App Store," and requires a legal entity (no DBAs or trade names), a D-U-N-S number, a work email on your company's domain and a public website on that domain.

That list takes days to assemble if you start from nothing, which is exactly why some agencies offer to publish under their own account "to save time." Don't take that offer. The account holds your app listing, your reviews and your users' trust in the seller name. If the relationship ends, moving an app between accounts is a process you do not want to be negotiating at the same time. Add your developer to your accounts with the access they need, and keep the owner seat. We cover the wider version of this, including who holds the repository and the cloud account, in the signs you have outgrown your agency.

A worked launch calendar

Picture a funded founder with no technical background launching a booking app for independent physical therapy clinics, on iOS and Android, with a public launch tied to a trade show date. Here is how the store gates change the plan, working backwards:

StepOwnerCalendar time
D-U-N-S number, company domain email, live websiteFounderStart in week 1 of the build, not the last week
Apple and Google accounts enrolled to the companyFounderOnce the D-U-N-S number is issued
Recruit 12 Android testers (clinic staff who agreed to try it)FounderBefore the build is feature-complete
Closed test on Google Play, 12 testers opted inDeveloper runs it, founder keeps testers active14 continuous days, per Google's rule (personal account)
Google production access reviewGoogle"Usually seven days or less"
Apple submission with demo account, account deletion, real privacy policyDeveloper, founder checks the listApple's typical figure is 90% within 48 hours
One rejection-and-resubmit cycleBothPlan for it: about 23% of 2025 submissions were rejected
Public launchFounderSet from the approval date, never the submission date

The point of the table is the left half of the timeline. If the founder starts the paperwork when the engineers say "ready," the stores add three weeks or more: Google's 14-day test, up to a week of production review, and a likely Apple resubmit. Started in week one, they add almost nothing, because the build covers the wait. Our post on how long an MVP takes to build covers the build side of the same calendar.

When a native app is the wrong answer

Here is the case where we would tell you not to build what you came to buy. If your product is mainly used at a desk, or the "app" would be your web dashboard with a login screen around it, guideline 4.2 is a real risk and the store gates add weeks for little gain. Ship it as a web app first, prove people use it, and build native when there is a reason a phone does it better: notifications that matter, the camera, offline use, location.

When the app really does need to be on a phone, plan the store work into the scope from the start rather than treating submission as an afterthought. Our mobile app development team includes store submission in the build, and a fixed-scope project under custom software development starts with an itemised estimate, which is where a launch date should come from. If you're weighing which engagement fits, fixed scope vs. a dedicated team sets out the trade. And if you have a launch date already and want to know whether it survives the store gates, send us the date and the build.

Sources

Written by Zain Ali

Frequently asked questions.

Apple's 2025 App Store Transparency Report says App Review rejected 2,093,244 of the 9,100,620 app submissions it reviewed in calendar 2025, about 23%. A submission is not the same as an app, because one app can be submitted several times and every update counts as a new submission. The 2024 report showed about 24.9%.

In Apple's 2025 App Store Transparency Report, the Performance section of the App Review Guidelines was cited in 1,354,418 rejections, more than any other section. That section opens with guideline 2.1, App Completeness, which asks for a working demo account, no placeholder content and an app tested on-device. A single rejection can cite more than one section.

Apple's App Review page, read in November 2026, says it typically reviews at least 50% of submissions in under 24 hours and 90% in under 48 hours, and that incomplete submissions may take longer. Apple does not publish a separate figure for a company's first app. A rejection adds the time to fix the issue and resubmit.

Google Play Console Help says developers with personal accounts created after 13 November 2023 must run a closed test with at least 12 testers opted in continuously for at least 14 days before applying for production access. Google says the production access review usually takes seven days or less. Organization accounts enroll differently and require a D-U-N-S number.

It is safer to enroll the Apple and Google developer accounts in your own company's name and give the developer access. Apple's organization enrollment page, read in November 2026, says the organization's name is displayed as the seller name on the App Store, and requires a legal entity, a D-U-N-S number and a company-domain email. Keeping the owner seat means the listing stays with you if the engagement ends.